Egypt’s Ministry of Water Resources and Irrigation has finalized 11 of 20 planned operations under the Kitchener Drain water-quality improvement initiative. The project aims to enhance agricultural drainage water reuse and improve water infrastructure across the Gharbia, Kafr El-Sheikh, and Dakahlia governorates.
Project Completion and Current Status
Minister Hani Sewilam reviewed the project’s progress during a recent ministry meeting. Completed works include the fortification of embankments, the rehabilitation of secondary drains, and the installation of water flow measurement equipment. The ministry has also protected slopes along the drain and upgraded various water structures to improve system efficiency.
Recent Contracts and Technical Support
The ministry has awarded two additional contracts that are currently undergoing finalization. These projects include on-farm irrigation upgrades covering 700 feddans and the construction of two pumping and mixing stations located in Samatay and El-Hamoul. A consultant has been appointed to provide technical supervision for the design and construction of these stations.
Upcoming Retendering
Four operations remain scheduled for retendering, according to the ministry. These include the rehabilitation of seven pumping stations and the upgrade of the Abu Skeen emergency center in Kafr El-Sheikh. Additionally, the scope involves dredging and embankment work across 46.7 kilometers of the Kitchener Drain and its branches, alongside the procurement of water-quality monitoring equipment.
Project Outlook
Minister Sewilam directed officials to expedite the remaining contracting procedures to maintain the project schedule. While 17 of the 20 planned operations have been accounted for through completion, contract awards, or planned retendering, the ministry did not specify the status of the final three projects or provide a total cost estimate.